New Housing Developments

Overview


Several new neighborhoods are coming to Rosemount this year.  A summary of each project is provided below.  If you have questions about any of these projects, please contact the Engineering Department at (651) 322-2022. 

Dunmore and Dunmore 2nd
Copper Creek Development received approval for 87-single family lots, located on the west side of Highway 3 just south of 132nd Street. There will be 30 lots in the first phase and 25 lots in the second phase. The remaining 32 homes will be developed in a future phase along with a pocket park, and will include a trail to connect to Lebanon Hills Regional Park to the north and south to Downtown Rosemount. Dunmore has two builders – Paragon Homes and Distinctive Design Build

Greystone 6th, 7th and 8th Additions 
This is the continuation of the Greystone development on the east side of Akron Avenue between Bonaire Path and CSAH 42.  The 6th addition includes 27 homes, the 7th addition includes 46 homes, and the 8th addition includes 25 homes, all by CalAtlantic Homes (Lennar).  Construction began on the 6th addition in summer, 2017 and will continue with the 7th and 8th additions through the 2019 construction season.


Harmony Villas and Harmony Villas 2nd
This development is on the north side of Connemara Trail, just east of TH3 in the Harmony development.  It will be completed in two phases, with 16 town homes in the first phase and 26 town homes in the second phase.  The developer is Mark Elliot Homes.

Meadow Ridge and Meadow Ridge 2nd
These developments are on the west side of Akron Avenue, north of Bonaire Path.  The first addition includes 34 single-family homes and the 2nd addition includes 29 single-family homes, all by developer Lennar.  Construction began on the first addition in summer, 2018 and will continue with the 2nd addition in spring 2019.

Prestwick Place 14th, 15th and 16th Additions
This is the continuation of the Prestwick development on the west side of Akron Avenue, north of Connemara Trail.  The 14th addition includes 38 homes, the 15th addition includes 39 homes, and the 16th addition includes 19 homes, all by Arcon Development (Prestwick LLC).  Construction began in summer, 2017 and will continue through the 2018 construction season.

Rosewood Crossings
This is a new apartment complex on the south side of 145th Street, just east of the railroad tracks.  The first phase will include two buildings, each with 32 units.  The developer is KJ Walk, Inc.  Construction will continue through the 2018 construction season.