Extension of Autumn Path

Overview

This project will construct a 42-foot wide collector roadway extension of Autumn Path, north of Bonaire Path and east of the Bella Vista development.  Pedestrian facilities will include a trail on the east side of the road and a sidewalk on the west side of the road.  Watermain will be installed the full length of the road, along with some sanitary sewer.  Storm pipe will be constructed to existing ponds.

Latest Updates

  • The contractor is completing final corrections and will be paving and striping by early fall.

Proposed Schedule

  • Construction Start - July 15, 2020
  • Public Assessment Hearing Continued - October 5, 2020
  • Open as Gravel Roadway - Mid-November 2020
  • Asphalt Paving and Substantial Completion - Spring/Summer 2021

Project Contacts

Please contact if you have questions about this project:

Brian Erickson, PE, City Engineer

(651) 322-2025 (office)

brian.erickson@ci.rosemount.mn.us