2021 Street Improvement Project

Overview

This project includes pavement rehabilitation on the streets show on the project map:

This project will also include sidewalk and curb spot replacement, minor utility work, as well as rehabilitation of pedestrian ramps to meet current requirements. 


Schedule
  • Neighborhood Meeting – October 8, 2020
  • Improvement Hearing – November 17, 2020
  • Accept Plans and Advertise Project for Bids – January 2021
  • Open Bids – February 2021
  • Assessment Hearing – March 2021
  • Construction Starts – Spring/Summer 2021
  • Construction Substantially Complete – Fall 2021